Site diary in pictures and words
25.01.2013. SETTING UP MODULE FOR SMART INSTALLATION SYSTEM
25.01.2013. IMAGES CONSTRUCTED FACILITY
06.11.2012. SETTING CLASSICAL PARQUET
02.10.2012. INSTALLATION OF SANITARY WARE IN THE BATHROOMS
28.09.2012. MAKING INTERIOR PLASTER COATING
27.09.2012. FINAL ROOFING-METAL WORKS
16.09.2012. MAKING WATERPROOFING TERRACE
06.09.2012. THE FINAL PHASE OF WORK ON THE FACADE
04.09.2012. WORK ON WARM-WATER CONNECTION AND THE SUBSTATION
24.07.2012. THERMAL INSULATION OF ATTIC
23.07.2012. MACHINE SMOOTHING
16.07.2012. CREATING DEMIT FACADE
15.06.2012. INSTALLATION OF CEMENT SCREED
30.05.2012. WORKS ON THE HEATING INSTALLATIONS
12.04.2012. MACHINE PLASTERING OF INTERNAL WALLS
05.03.2012. A SAMPLE OF PVC JOINERY
02.03.2012. ELECTRICAL INSTALLATIONS
30.12.2011. INSTALLATION OF VERTICAL INSTALLATION OF VATER SUPPLY AND SEWERAGE
13.12.2011. BUILDING THE WALLS
10.12.2011. INSTALLATION OF ROOF WINDOWS
01.12.2011. COVERING THE OBJECT
19.11.2011. MAKING WOODEN ROOF STRUCTURE
31.10.2011. FORMWORK CONCRETE STRUCTURES FOR THE RECEPTION OF THE WOODEN ROOF CONSTRUCTION
30.09.2011. CONCRETE SLAB ATTIC
14.09.2011. THE FORM OBJECT IN SPACE
06.09.2011. CONCRETING OF THE THIRD FLOOR PLATE
17.08.2011. CONCRETING OF THE SECOND FLOOR PLATE
11.08.2011. PREPARATION FOR CONCRETE SLAB OF THE SECOND FLOOR
03.08.2011. PREPARATION FOR CONCRETE COLUMNS AND WALLS OF THE FIRST FLOOR
01.08.2011. CONCRETING OF THE FIRST FLOOR PLATE
30.07.2011. REINFORCEMENT SLAB OF THE FIRST FLOOR
26.07.2011. PREPARATION OF FORMWORK FOR CONCRETE SLAB OF THE FLOOR 1
18.07.2011. CONCRETING OF GROUND FLOOR PILLARS USING CONCRETE PUMP
14.07.2011. INSTALLATION OF FORMWORK FOR PILLARS AND GROUND FOUNDATION
12.07.2011. CONCRETED ZERO PLATE (GROUND FLOOR PLATE)
05.07.2011. MOUND OF SAND BETWEEN THE FOUNDATION WALLS
04.07.2011. THE FOUNDATION WALLS AND PILLARS
30.06.2011. PREPARED FORMWORK FOR CONCRETE FOUNDATION WALLS AND PILLARS, TO THE ZERO PLATE
28.06.2011. REINFORCEMENT AND FORMWORK SET UP BETWEEN THE BASE PLATE AND GROUND FLOOR SLABS
24.06.2011. THE BASE PLATE CONCRETING
17.06.2011. INSTALLATION OF REINFORCEMENT FOR THE BASE PLATE
16.06.2011. DETERMINED THE EXACT POSITION OF AN OBJECT IN SPACE, ARRIVED THE FIRST SHIPMENT OF CONCRETE ARMATURE
15.06.2011. THIN LAYER OF CONCRETE
14.06.2011. EMBANKMENT FOUNDATION PIT WITH GRAVEL
11.06.2011. BACKFILING THE EXCAVATION WORKS ON IBERLAUF
08.06.2011. EXCAVATION OF LAND FOR A BASE PLATE
06.06.2011. START OF PREPARATION WORKS