Site diary in pictures and words


25.01.2013. SETTING UP MODULE FOR SMART INSTALLATION SYSTEM

25.01.2013. IMAGES CONSTRUCTED FACILITY

06.11.2012. SETTING CLASSICAL PARQUET

02.10.2012. INSTALLATION OF SANITARY WARE IN THE BATHROOMS

28.09.2012. MAKING INTERIOR PLASTER COATING

27.09.2012. FINAL ROOFING-METAL WORKS

16.09.2012. MAKING WATERPROOFING TERRACE

06.09.2012. THE FINAL PHASE OF WORK ON THE FACADE

04.09.2012. WORK ON WARM-WATER CONNECTION AND THE SUBSTATION

24.07.2012. THERMAL INSULATION OF ATTIC

23.07.2012. MACHINE SMOOTHING

16.07.2012. CREATING DEMIT FACADE

15.06.2012. INSTALLATION OF CEMENT SCREED

30.05.2012. WORKS ON THE HEATING INSTALLATIONS

12.04.2012. MACHINE PLASTERING OF INTERNAL WALLS

05.03.2012. A SAMPLE OF PVC JOINERY

02.03.2012. ELECTRICAL INSTALLATIONS

30.12.2011. INSTALLATION OF VERTICAL INSTALLATION OF VATER SUPPLY AND SEWERAGE

13.12.2011. BUILDING THE WALLS

10.12.2011. INSTALLATION OF ROOF WINDOWS

01.12.2011. COVERING THE OBJECT

19.11.2011. MAKING WOODEN ROOF STRUCTURE

31.10.2011. FORMWORK CONCRETE STRUCTURES FOR THE RECEPTION OF THE WOODEN ROOF CONSTRUCTION

30.09.2011. CONCRETE SLAB ATTIC

14.09.2011. THE FORM OBJECT IN SPACE

06.09.2011. CONCRETING OF THE THIRD FLOOR PLATE

17.08.2011. CONCRETING OF THE SECOND FLOOR PLATE

11.08.2011. PREPARATION FOR CONCRETE SLAB OF THE SECOND FLOOR

03.08.2011. PREPARATION FOR CONCRETE COLUMNS AND WALLS OF THE FIRST FLOOR

01.08.2011. CONCRETING OF THE FIRST FLOOR PLATE

30.07.2011. REINFORCEMENT SLAB OF THE FIRST FLOOR

26.07.2011. PREPARATION OF FORMWORK FOR CONCRETE SLAB OF THE FLOOR 1

18.07.2011. CONCRETING OF GROUND FLOOR PILLARS USING CONCRETE PUMP

14.07.2011. INSTALLATION OF FORMWORK FOR PILLARS AND GROUND FOUNDATION

12.07.2011. CONCRETED ZERO PLATE (GROUND FLOOR PLATE)

05.07.2011. MOUND OF SAND BETWEEN THE FOUNDATION WALLS

04.07.2011. THE FOUNDATION WALLS AND PILLARS

30.06.2011. PREPARED FORMWORK FOR CONCRETE FOUNDATION WALLS AND PILLARS, TO THE ZERO PLATE

28.06.2011. REINFORCEMENT AND FORMWORK SET UP BETWEEN THE BASE PLATE AND GROUND FLOOR SLABS

24.06.2011. THE BASE PLATE CONCRETING

17.06.2011. INSTALLATION OF REINFORCEMENT FOR THE BASE PLATE

16.06.2011. DETERMINED THE EXACT POSITION OF AN OBJECT IN SPACE, ARRIVED THE FIRST SHIPMENT OF CONCRETE ARMATURE

15.06.2011. THIN LAYER OF CONCRETE

14.06.2011. EMBANKMENT FOUNDATION PIT WITH GRAVEL

11.06.2011. BACKFILING THE EXCAVATION WORKS ON IBERLAUF

08.06.2011. EXCAVATION OF LAND FOR A BASE PLATE

06.06.2011. START OF PREPARATION WORKS