06.09.2011.
Today is concreted the third floor plate. For concreting of the slab spent 65m3 pumped concrete mark 30 with 3 fractions. The concrete details can be seen ...
30.08.2011.
Arrived the report on the results of geotechnical control tests. According to the report, resulted in improved capacity after replacement of soil, so it now meets the generated load in comparasion to ...
17.08.2011.
Today is concreted the second floor plate. For concreting of the slab spent 65 m3 of concrete mark 30 with 4 fractions. As before, concrete is made using concrete pumps. Photos and video from the ...
02.08.2011.
Today is concreted the first floor plate. The thickness of the slab is 20 cm, and for her concreting spent 64 m3 of pumped concrete mark 35, with 3 fractions. Photos can be viewed ...
12.07.2011.
Today is concreted zero plate (ground floor plate). For more information see ...
24.06.2011.
Today is concreted base plate. The thickness of the slab is 40 cm and its concrete has spent about 100 m3 of concrete marks 30. Concreting was carried out with the help of concrete ...
20.06.2011.
After concreting thin layers of concrete, began installation of reinforcement and preparation for concreting of the base ...
16.06.2011.
Today, the surveyer determine the exact position of an object in space. Also, today arrived first shipment (16.000 kg) of concrete reinforcement mesh and iron, complete fittings to ...
15.06.2011.
After completion of filling and compacting buffer layer, and compressibility module checks by authorized organizations (which shall promptly report to come), they are now thin layer of concrete, ...
11.06.2011.
After completing the excavation for the foundation slab the object, through visual inspection of the bottom of the excavation, it was concluded that the ground is unstable, due ...